Rice & Gardner served as the Commissioning Provider for the office tenant improvements located on the fourth floor of the Boeing Tower II in Clear Lake City. Tenant improvements include 16,000 SF of minor revisions to the existing HVAC system with an added split system for the IT room.

Rice & Gardner provided fundamental commissioning services during the design and construction phase which included leading, reviewing, and overseeing the completion of the commissioning process activities.

Systems commissioned included: Air handling unit, terminal units, split system, and lighting control system via occupancy sensors.

Additional Information
  • Provided documented confirmation that the facility fulfills the functional and performance requirements of the Owner, designer, occupants, and operators
  • Prepared commissioning specifications/requirements and reviewed the design to ensure it meets the Owner’s objectives
  • Developed and coordinated the execution of a testing plan, including observing and documenting all systems’ performance to ensure that the systems are functioning in accordance with the Design Intent requirements and the Contract Documents.
  • Developed and administered Deficiency Logs
  • Developed OPR, BOD, Commissioning Plan, Specifications, and Issued final Commissioning Report